Electrical Commissioning Supervisor for Hire

04:18 in Electrical Engineer, Member by Mohd Redzuan Bin Ani

PERSONAL DETAIL

Name :Mohd Redzuan Bin Ani
Email :mohdredzuanani@yahoo.com
ID Card Number :800728 – 02 – 5645
H/Phone Number :012 – 4877226
Address :No 47 Lorong 33, Taman Gurun Jaya,
08300, Gurun, Kedah Darul Aman
Nationality : Malaysian
Race : Melayu
Religion : Islam
Health Condition : Good

PERSONAL STRENGTH

Comfortable working in group and able to related with everybody at any level
Able to meet tight datelines and working under pressure
Dedicated, motivation and hardworking work

EDUCATION BACKGROUND

Diploma Of Electrical Engineering Power
UTM – Kolej Negeri ( 2000 – 2003 )

Traning :
Has attend one day course on Numberical Protection, Short Circuit Current And Power Factor control.

Has attend one day seminar on Electro-Mechanical Motor Starter solution Coordination and Protection.

Skill for Computer : word/excel/powerpoint

WORKING EXPERIENCE

Team Force Engineering Services Sdn Bhd
( Dec 2003 To Now )

Position : Supervisor ( Commissioning and ReCalibration )

Experience : 6 Years

Job Discription;

Supervise to commissioning Pencawang Pembahagian Utama, Stesen Suis Utama, ( 33kv & 11kv ) . 33kv & 11kv Cable and Power Transformer.

1.To Check protection, Functional and operation the system
PROTECTION
To check overcurrent & earthfault , current diff. , motor protection, undervoltage and Overvoltage
etc. ( ABB, SEIMENS, REYROLL, AREVA )

FUNCTIONAL
To check Alarm, facia ( indicator ), scada and trip & intertrip

OPERATION
To check close and open circuit breaker by local, remote and scada ( supervisory )
To check interlocking system by mechanical and electrical.

2.Commissioning Power cable and power transformer

POWER CABLE
To do insulation resistance test and phasing check
To check outer shealth and conductor XLPE and PAPER cable

POWER TRANSFORMER
To check IR for winding
Check the ratio transformer
Check Impedance and stability transformer
Check functional for alarm and tripping
example; Tempreture, bulchoz, pressure relief etc.

  • Share/Bookmark

Experienced electrical engineer for Hire

15:34 in Electrical Engineer, Member by Ikhwan Alhany

to be included

  • Share/Bookmark

Experience Electrical /Instrument /Gas Turbine Specialist for hire

12:30 in Electrical Engineer, Member by wan mustafa

NAME : WAN MUSTAFA WAN JUSOH

EDUCATION:

Qualification : Cert. Of Electrical Engineering
Major : Industrial Motor Control
Technical Courses : Electrical Installation & Maintenance.
Instrumentation & Motor Control

PERSONAL PARTICULARS

Age : 42 years Date of Birth : 18 April 1966
Gender : Male Passport No : A 13349242
Marital Status : Single ID No : 660418-11-5045
Permanent Residence : Malaysia Nationality : Malaysian

ADDRESS

Current Address : A- 10 – 14, Apartment Plaza 393
Peel Road, Cheras
50088, Kuala Lumpur
MALAYSIA

Permanent Address : 39 – D, Kenanga Road
Sura Jati
23000 Dungun
Terengganu
MALAYSIA

Tel (Home) : 609-8456179
Tel (Mobile) : + 6 019-8388-585

E-Mails add. : wanzero1@gmail.com

WORKING EXPERIENCES / PREVIOUS EMPLOYMENTS ( Between year 2000 till present)

1 . Company’s Name : PETRONAS MDD Project, MLNG 2, Bintulu, Sarawak
Position : Electrical Commissioning Supervisor.
Date Joined : September 2009 till present.

Work’s descriptions

- To do a pre-comm, start-up and commissioning works on GE gas turbine generators (25MW )
- Power distributions, Generators and transformer protections , Nuovo Pignone compressors (HV motor driven) and plant’s electrical equipments start-up and commissioning works.

2 . Company’s Name : GENERAL ELECTRIC COMPANY – GE Energy Oil & Gas.
Position : Field Service Engineer / Technical Advisor. (Instrumentation & Electrical)
Date Joined : 1st December 2004 to 31st May 2008
Person for reference: Gianni Marziali, Asia Pacific Service Manager, GE Energy Oil & Gas.
+6012 3031 357,

- Job’s assignments & work completions

July 3rd, 2006 till February 23rd 2008 – Shinryo – Streamline Consortium S/B Cogeneration Project.

- Assigned for a new installations of four units Gas Turbo- Generators (25 MW) , MS 5002 E , Frame 5 at
- PETRONAS Melaka Cogeneration Project.
- Directly involved during construction, pre-comm. and Start –up and commissioning stages.

…………………………………………………………………………..

September 30th, 2006 to January 7th, 2007 – THAI Oil Company, Sri Racha, Thailand.

- Assigned for a new installation of one (1) unit MS 6001 B , 42 MW Gas Turbo Generator for THAI Oil
- Company in Thailand.
- Directly involved during constructions and pre- commissioning stages.

…………………………………………………………………………….

March 26th, 2006 to April 15th, 2006 – MLNG 3, Bintulu, Sarawak.

- Supervise for major shutdown works (Hot Gas Path Inspection) for four (4) units of MS 5002 D Gas Turbo-
- Generators and two (2) units of MS 6001 and MS 7001 E, Gas Turbo-Compressors.

……………………………………………………………………………

February 22nd, 2006 to May 1st, 2005 – ESSO Petroleum Refinery, Sri Racha, Thailand.

- To perform and up rated MS 5001E DLN Nox and WLN Nox systems.
- Site surveys for MS 6001 Turbo-Generator’s enclosure ventilations up grades.
- MK V firmware upgrades.

- Page 1 -

May 27th, 2005 to February 1st, 2006 – TPPI Aromatic Plant, Tuban, Jawa Timur, Indonesia.

- Assigned for a new installation of five (5) units of MS 5002E Double Fuel Turbo – Generators (25 MW)
- Directly involved for all field instrumentations and Electrical equipments start-up and commissioning works.

………………………………………………………………………………………………….

March 11th, 2005 to April 18th, 2005 – SEPCO Power Plant, Guang Dong, Nanhai, Republic of China.

- Doing start-up and commissioning works for MS 5001E Turbo-Generators electrical protection systems.

……………………………………………………………………………………………………

Field Service Engineer / Technical Advisor specific duties

- Perform a specific work tasks for site and client specific project requirements.
- To give and execute jobs for and to the customers accordingly as per contractual agreements
- Strong technical knowledge and able to solve any technical related issues on company’s products…
- Well prepared and organized in order to manage the job site’s requirements as well as to establish good working relations with customer / client.
- Professionalism is always a part of a working culture.

- Page 2 –

3. Company’s Name : SERBA DINAMIK S/B, Bintulu, Sarawak.
Position : Electrical & Instrument Specialist. (Rotating Equipments)
Date Joined : April 2003 to June 2004.

Job’s assignments / work completions

April 2003 to September 2003 – MLNG 1, 2 & 3, Bintulu, Sarawak.

- Doing a schedule Gas Turbine’s shutdown works and other plant’s maintenance works.
- Turbine’s Control systems troubleshooting works.

…………………………………………………………………………………

September 2003 to October 2003 – QATAR GAS, Ras Laffan, Qatar.

- Lead and supervised a team of skilled technicians for all Instrument & Electrical related works.
- For 6 units of MS 7001E Gas Turbo Compressors up rating to EA in accordance with plant’s de-bottlenecking works on Train 2.

……………………………………………………………………………………

November 2003 to February 2004 – Abu Dhabi National Oil Company, Emirates. Bahrain, Oman & various refinery plant in Saudi Arabia.

- Assigned to Nuovo Pignone Field Services (Italy) for schedule shutdown works for MS 5001, PGT 25, LM 200 turbines in various job locations in Saudi Arabia regions.

………………………………………………………………………………..

April 2004 to June 2004. – QATAR GAS, Ras Laffan, Qatar.

– Lead and supervised a team of skilled technicians for doing all Instrument & Electrical related works
- For 6 units of MS 7001E Gas Turbo Compressors up rating to EA in accordance with plant’s de-bottlenecking works on Train 3.

…………………………………………………………………………………….

- Page 3 –

4 . Company’s Name : KENTZ (MEPC) Malaysia S/B ., Bintulu, Sarawak.
Position : Lead Electrical & Instrument Expertise – Rotating equipments.
Date joined : March 2002 to April 2003.

Job’s assignment / task

- To performs a start-up and commissioning works on all Gas Turbines at MLNG 3 train 7 and 8 and five
- Units of MS 5001 Gas Turbo Generators, which follows accordingly as per strict procedures given by the owner.
- The works includes set-up, functional tests of plant’s complex process logic interfaces and full functionality of turbine’s safe guarding systems and a systems configurations for turbine’s HMI MK V Speedtronic .
-

…………………………………………………………………………………..

5 . Company’s Name : CARIMIN S/B , DUYONG Platform , Petronas Carigali D12 Zone, Terengganu
Position : Instrument & Control Tech. – Rotating Equipments
Date joined : August 2000 to August 2001

Job’s assignment / task

- Attached to Petronas Carigali at Duyong offshore platform .
- Job as a technical supports to Petronas Carigali Instrument and Control technical team which is only specific to platform’s turbine compressors and turbine generators.(SOLAR , PRATT & WHITTNEY
- & ROLL – ROYCE )
- To do maintenance and perform troubleshooting during process upset or turbine units shutdown.
- Also assigned to the other Petronas’s platforms upon requisition from Petronas Kerteh .

…………………………………………………………………………………………..

- Page 4 –

SUMMARY

- Start to work in oil & gas industries at the age of 20 years old in 1986 as an Electrician.
- Most of the employments are under contractual basis, a normal working standard for freelance.
- Having a good technical knowledge and hands on experiences in both Instrumentation and Electrical.
- Very well familiar with oil & gas standards which comply with Health & Safety issues.

  • Share/Bookmark

Electrical Commissioning Supervisor for hire

01:19 in Electrical Engineer, Member by Aris Izzuddin

CURICULUM VITAE

A. PERSONAL PARTICULARS

Name: MUHAMMAD ARIS IZZUDDIN SREEDHARAN BIN ABDULLAH

Date & Place of Birth: 11th JUNE 1971 / KEDAH, WEST MALAYSIA.

Identification Card Number: 710611-02-5933

Nationality: MALAYSIAN

Correspondence Address: No. 295, Jalan Tun Hussien Onn,
Taman Jasmine, 97000 Bintulu,
Sarawak East Malaysia.

Mobile Phone No: +60167618687.

Email Address: aris_izzuddin@yahoo.co.uk
mlng_tiga@yahoo.com
aris_izzuddin@hotmail.com

B. Education

School / Institution Year Level

Sekolah Menengah Kuala Ketil, Kedah 1988 SPM (MalaysianEducationCerificate)

C. PROFESSIONAL EXPERIENCE

Organization Year Post Held

MLNG DUA DE-BOTLENECKING 2007 – 2009 Electrical Supervisor
PROJECT (Integrated Project Commissioning, Construction
Management Team – IOPMT). & maintenance of electrical
installation up to 33kV

KELLOG, BROWN & ROOT 2004 – 2006 Senior Electrical Supervisor
(JEPAK HOLDINDS SDN. BHD.) Commissioning, Construction
& maintenance of electrical
installation up to 33kV

SAFF TASS SDN. BHD. 2000 – 2003 Electrical Supervisor
Testing, commissioning &
maintenance of electrical
installation up to 132kV.

COLDWIND M&E SDN. BHD. 1997 – 2000 Electrical Supervisor
Supervising & coordinating
Installation & servicing
of Air Conditioning units.
(split unit type, domestic
and commercial)

ELECTEST SDN. BHD. 1992 – 1997 Senior Technician/Team Leader
Testing, commissioning &
maintenance of electrical
installation up to 132kV.

SEAGATE TECH. INTERNATIONAL 1989 – 1992 Facilities Technician
SINGAPORE Maintenance and up keeping
of facilities/production
equipment.

Duties & Responsibilities Held in MDD Project

• Involve in Commissioning of ABB Electrical Network Management Control
System.

• Generator Control and Protection System.

• 6.6KV / 33KV & 415V Distribution and Protection System.

• To coordinate installation, testing, commissioning & servicing of
protection relays, switchgears, transformers and other electrical
equipment & instruments.

• To do planning of installation, testing, commissioning & servicing works
such as:
a. Coordination of job & planning with the contractors.
b. Preparing all equipment for the required job are available
and in good condition with the necessary documentations.
c. Preparing & making sure all safety equipment (PPE) which
needed especially for the workers who are working under my
supervision are complete and in good condition.
d. To make job schedules.
e. To make manpower planning.
f. To prepare documents such as test forms, procedures, manuals
& etc.

• To supervise & implementing safety for works done by contractors:
g. All safety procedure followed accordingly.
h. All works ongoing are on schedule.
i. Ensuring the safety of workers and equipments.

• Submitting all records & documents needed in the completion of work to
the QA/QC & Commissioning Engineer.

• Making sure of all contractor’s testing equipment are always in good
condition and ready.

• Making sure of all critical contractor’s test equipment’s calibration
certificates are valid and has not expired.

• To review & comment contractor’s work procedures and test form required
for all present or future works.

• To give training and guidance to the contractor’s worker under my
supervision.

• To supervise contractor’s workers discipline under my supervision.

• To send report to the contractor whenever there is a defect or
construction error at the related job site.

• To make sure all construction work are done accordance the
specifications required before starting any testing & commissioning
works.

• To meet with QA/QC requirement at work site.

• Follow the rules & regulations of the company policy.

PROFESSIONAL SKILLS

1. Able to carry out testing and other related jobs independently.

2. Experienced in operating, testing, calibrating, maintenance & servicing
of:
• Electrical switchgears, circuit breakers & bus bars from 415 V to
33 kV. (ABB, Tamco, Siemens, EPE, Merlin Gerin & etc.)

• Electrical Transformers & Transformer Protection (Buchholtz, Oil
Temp, Winding Temp, Pressure relief & etc.)

• Protection relays; Over Current Protection, Earth fault
Protection, Voltage Protection, Frequency Protection, Motor
Protection;

4. Generator Protection;

5. Pilot wire Protection

6. Bus-bar Protection

7. Breaker Failure Protection

8. Transformer Differential Protection

9. Experienced in simulating & checking switchgear switching philosophy
according to specification required;
• Inter-trip philosophy & sequence.
• Earthing philosophy & sequence.
• Interlocking philosophy & sequence
• Load shedding philosophy & sequence

10. Able to trouble-shoot switchgear control and protection circuit.

11. Very versed in operating any testing equipment such as;
• Single phase secondary current injector.
• Three phase secondary current injector.
• Conductivity tester.
• Hipot tester AC/DC
• Primary current injector.
• Oil dielectric strength tester.
• Insulation tester & etc.

12. Computer literate on Microsoft Word, Microsoft Excel, Testing equipment
with software controls & etc.

13. Experienced in installing, maintenance & servicing of split type air’
conditioning unit.

Projects & Job involved 2001 – Present

PETRONAS MLNG TIGA Project in Bintulu, Sarawak. 2001 – 2006

1. Executed all testing of protection relays, switchgears, transformers and
other electrical installations & instruments.

2. Involving in the testing & commissioning of MLNG TIGA (Petronas) project
in Bintulu, Sarawak, Malaysia.
• ABB INSUM 2 / MCU 2
• ABB SPACOM RELAYS, Spaj 140C, 110C, 115C, 111C, Spau 140C, Spad 346
etc.
• ABB REF 542 RELAYS
• REL 316*4 (Line differential)
• REG 316*4 (Generator protection)
• GE MULTILIN 489 & etc.

3. High voltage testing of switchgears, bus bars, circuit breakers and
cables from 6.6 kV to 33kV 50Hz system and also 6.6 kV 60Hz (LCI)
system.

4. Power transformer testing including differential stability check.

5. Stability check on 11kV motor on differential protection.

6. Motor protection & motor starter functional check.

7. Assisted ABB & SIEMENS vendor to do testing work & commissioning.

8. Assisted ABB vendor to test & commission ENMC system.

9. Functional check on all switchgear switching philosophy, operating
function and internal circuit check.

10. Commissioning of ABB Electrical Network Management Control System

SHELL CAMPION 7 Offshore Platform, Brunei.2003

1. Assisted ABB Australia to test & commission 11kV system switchgear &
cables for the water injection plant.

2. Tested & commissioned REF 542 PLUS relays.

3. Functional check on all switchgear switching philosophy, operating
function and internal circuit check.

4. Motor protection & motor starter functional check

5. High voltage testing of 11kV system switchgears, bus bars, circuit
breakers and cables.

6. Functional check on all switchgear switching philosophy, operating
function and internal circuit check.

Other Jobs involved

New & Turnaround Yearly Servicing

1. MLNG 1&2 MRR project

2. GDC (Gas & District Cooling) KLIA Sepang Kuala Lumpur, Malaysia.

3. GDC (Gas & District Cooling) Putrajaya, Kuala Lumpur.

4. GDC (Gas & District Cooling) KLCC, Petronas Twin Towers, Kuala Lumpur,
Malaysia.

5. BSAF (M) Sdn. Bhd. (chemical plant) Johor, Kuala Lumpur & Kuantan,
Malaysia.

6. IDEMITSU SM (M) Sdn. Bhd. (Chemical Plant) Johor, Malaysia.

7. Petronas Melaka Refinery PPMSB. (oil refinery) Melaka, Johor.

8. Petronas Kertih Refinery. Terengganu, Malaysia.

9. Petronas Carigali. Offshore platforms. Malaysia.

10. University Technology Malaysia. Johor, Malaysia.

11. Titan (M) Sdn. Bhd. (cracker & Polyethylene plant)

12. Sime Sembawang Ship Yard. (Platform fabrication) Johor, Malaysia.

13. MSE Sdn. Bhd. (Platform fabrication) Johor, Malaysia.

14. University Islam Antarabangsa, Kuala Lumpur.

  • Share/Bookmark

12 years experienced Electrical/ Protection/ Testing Engineer for hire

09:26 in Electrical Engineer, Member by mojoflyer

S.N.CHEONG (Mr.)
csnang@hotmail.com

Profile Summary

Electrical engineer highly skilled and experienced working in fast paced environment demanding strong technical skills. Trustworthy, diligent and resourceful, able to multi-task and effectively. Capabilities include:

For Electrical switchgear, protection relays, power transformers, power cables, MCC, Drives etc from 415V to 33kV.
. Design Switchgear
. Testing/ Programming
. Perform Maintenance
. Troubleshoot/ Fault investigation
. Commissioning
. Team leading

Experience Highlights

Electrical Commissioning Engineer
. Malaysia LNG – 6.6kV & 33kV Switchgear & ABB REF542+ relay specialist
. DQ Refinery, Vietnam – 415V MCC & 6.6kV switchgear(ABB)
. PETROBRAS FPSO, Singapore – 11kV switchgear & Generator protection and control panel(GCPP)
. Uong Bi Power Station, Vietnam – 11kV switchgear(ABB)
. Melaka Cogen, Malaysia – 33kV GIS & 6.6kV switchgear
. SMART Tunnel, Malaysia – 33kV GIS & AIS switchgear

Electrical troubleshoot/ fault investigation Engineer
. Keppel FPSO, Singapore – ABB REM/REG543 protection relays programming troubleshooting
. Air Liquide, Vietnam – Auto transformer & power reactor fault investigation & commissioning
. SB International Airport, Thailand – Transformer protection mal-tripping fault investigation
. Beaufort Water Treatment, Malaysia – Vacuum contactor flash-over investigation.

Electrical  engineer
. ABB, Malaysia – Testing/service engineer for 415V MCC and switchgear up to 33kV, ABB protection relays specialist (REF542+,REM/REF545 etc.)
. ABB, Malaysia – Switchgear design engineer( 3.3kV to 33kV AIS, GIS)
. SFG, Malaysia – Protection relays specialist for SEG(Germany) relays
. Electest, Malaysia – Testing/ maintenance engineer for switchgears, transformers, power cables, MCC, drives etc.

Employment History

ABB Malaysia, Design engineer, testing/service senior engineer, Relay specialist
SFG Malaysia, Protection relays specialist for SEG(Germany) relays
Electest Malaysia, Testing engineer

Education
Institute Megatech, Malaysia (1996-1998)
Higher Diploma in Electrical & Electronic Engineering

College Damansara Utama, Malaysia (1994-1996)
Diploma in Electrical, Electronic & Telecommunication Engineering
Significant achievements
. Successful troubleshooting of mal tripping of transformer differential protection and motor earth fault protection for 7MW motor in MLNG by analyzing the fault record data. Redesigned the protection scheme to allow successful start up and commissioning of the motor as scheduled.
. Successful commissioning of 415V MCC and switchgear ahead of schedule for DQR, Vietnam project and successful troubleshooting of transformer differential protection instability.
. Achieved significant quality improvement of switchgear during service with ABB Malaysia.
. Successful root cause finding with detailed waveform analysis report for flash over incident of auto transformer in Air Liquide, Vietnam.

  • Share/Bookmark